Precautions for safe operation of truck-mounted drilling rig
Release time:
2020-05-16
The 150-meter drilling rig is suitable for water wells, engineering geological exploration and other drilling holes and various concrete structure inspection holes. According to the geological structure, the 150-meter drilling rig can be drilled with drill bits such as diamond, alloy and steel. Today, according to the small make up to understand the drilling rig operating instructions.
150 m drilling rig operating instructions:
1. Before use, check the flexibility of the air motor rotation, remove obstacles within the working range of the 150m drilling rig and walking road, and check the passing capacity of the road. Drilling tools, propulsion mechanisms, electrical systems, pressure systems, piping and dust protection devices.
2. Prepare the cave. The size of the cave can be determined according to the perforation method. Typically, when a horizontal hole is drilled, the height of the cave is 2.6-2.8 meters. When drilling, the width of the cave is the lower hole or the inclined hole. It is 2.5 meters and the height is 2.8-3 meters.
3. Guide gas and water pipes, lighting lines, etc. to the working surface for use.
According to the design requirements of the hole, the pillar is firmly erected. The upper and lower ends of the pillars shall be covered with planks. The horizontal shaft and snap ring are installed on the pillar according to a certain height and direction. Lift the machine through a manual winch, fix it on the pillar at the desired angle, and then adjust the hole of the drill bit.

5, open the hole. Drill out the drive fan and rotary mechanism, pull the impactor operation valve to the half-open position; open the lifting button of the lifting propulsion mechanism, and lower the drilling tool of the down-the-hole machine. When the drill bit hits the rock. The impactor starts working and opens.
6. During the drilling process, the motor or rotating reducer must not be reversed, and the drill should be prevented from tripping.
7. Before adding the drill pipe, the center hole of the drill pipe should be cleaned to prevent dust from entering the impactor.
8. The drill bit should be replaced immediately, and the diameter of the drill bit should not be larger than the diameter of the original drill bit.
9. When a stuck drill occurs, the thrust should be reduced immediately, and the rotation and flushing should be strengthened to gradually return to normal. If the card is severely drilled, it must be stopped immediately. Use the tool to increase torque and tension to loosen the drill bit. Then, while the wind blows, the drill will drill until it returns to normal.
10. Stop the drilling tool, pull the main switch to the automatic position, push the control valve handle to the down position, and perform pressure rock drilling.
11. The 150-meter drilling rig should always adjust the tightness of the steel wire rope of the propulsion mechanism to improve the reliability of the operation of the upper and lower stroke switches of the pulley block; if it is not correct, it should be repaired in time.
12. When the rig is displaced, the bracket and boom should be adjusted to maintain the balance of the body. If it is rock or broken rock, the yellow mud should be put into the protective hole.
13. There must be no shortage of oil during operation. After the operation is completed, the drilling rig is cleaned and lubricated.